Intersection Improvements

As one of the busiest and most accident-prone intersections in the City, the Holden Boulevard / South Gilmore Road / Route 4 Intersection Improvement Project’s aim is to improve both the flow of traffic and the safety of those entering the intersection. The ODOT Central Office Safety Program has already awarded $2.4 million dollars in funding.

Purpose

Prior to the completion of detailed studies and engineering design, the plan is to widen the intersection to accommodate additional turn lanes onto Route 4 and an additional through lane from Holden to South Gilmore. The traffic signals will be upgraded to include mast arm signals and illuminated advance lane use signs. Average daily traffic is approximately 13,670 along South Gilmore, 13,880 along Holden Boulevard., and nearly 35,000 along Route 4. The traveling public can expect significant disruption at this intersection. Parkland Hills Drive will be closed for some of the project to accommodate the realignment of South Gilmore Road. Access to all businesses will remain open for the duration of the project. Bronze certified logoThis project was assessed by the Greenroads (PDF) rating system and achieved a Bronze rating.

  • Project Bid: March, 8 2016
  • Bid Price: $2,056,329.28
  • Final Cost: $1,843,551.79
  • Contractor: JR Jurgensen
  • Completion: November 30, 2016