With the ever growing concerns about environmental hazards, it is critical that we at the City of Fairfield Wastewater Treatment Facility do our part in being environmentally friendly. Protection of the receiving waters is our #1 goal here at the facility.
The wastewater treatment industry is rapidly changing. Restrictions on effluent quality are increasing, Biosolids programs are changing, technology is moving forward, and the facility and collection system's infrastructure is growing in age.
The staff at the City of Fairfield Wastewater Treatment Facility takes great pride in staying one step ahead of the ever growing demands and changes in the wastewater treatment industry. Below is a list of some Capital Improvement Projects and their costs coming up in the near future.
2013
| Sanitary Sewer Rehabilitation |
$200,000 |
| Root Control Program |
$25,000 |
| Manhole Rehabilitation Program |
$30,000 |
| Channel Grinder Overhauls |
$21,000 |
| Plant SCADA System Replacement |
$15,000 |
| Software/GIS Aerials |
$8,750 |
| Dystor Dome Replacement |
$450,000 |
| Monitoring Equipment |
$6,000 |
| Generator Installation and Motor Control Center |
$2,500,000 |
| UV Lamp Replacement |
$20,000 |
| Update Sanitary Sewer Hydraulic Model |
$45,000 |
| Instrumentation Replacement Program |
$30,000 |
| Seward I Lift Station Relocation |
$300,000 |
| Fine Screen Overhaul |
$90,000 |
| Boiler Replacement/Maintenance |
$30,000 |
2014
| Sanitary Sewer Rehabilitation |
$200,000 |
| Root Control Program |
$25,000 |
| Manhole Rehabilitation Program |
$30,000 |
| Channel Grinder Overhauls |
$22,000 |
| Pump Overhaul/Replacement Program |
$17,000 |
| Monitoring Equipment |
$12,000 |
| Primary Tank Overhaul |
$40,000 |
| Anaerobic Digester Cleaning |
$15,000 |
| Pavement Repairs and Replacement |
$25,000 |
| Remodel Lab |
$20,000 |
| TVing and Sewer Cleaning Equipment |
$6,000 |
| Dystor Dome Replacement |
$450,000 |
| Instrumentation Replacement Program |
$15,000 |
| Aeration System Diffuser Replacement |
$42,000 |
| Biosolids Storage Building |
$250,000 |
2015
| Sanitary Sewer Rehabilitation |
$200,000 |
| Root Control Program |
$25,000 |
| Manhole Rehabilitation Program |
$30,000 |
| Channel Grinder Overhauls |
$23,000 |
| Pump Overhaul/Replacement Program |
$17,000 |
| TVing and Sewer Cleaning Equipment |
$35,000 |
| Monitoring Equipment |
$12,000 |
| Biological Nutrient Facilities |
$80,000 |
| Aeration Panel Replacement |
$25,000 |
| Instrumentation Replacement Program |
$15,000 |
| Anaerobic Digester Cleaning |
$15,000 |
| Sanitary Sewer Extensions |
$625,000 |
| Equalization Basin Liner Replacement |
$250,000 |
| Digester Facade |
$35,000 |
|