With the ever growing concerns about environmental hazards, it is critical that we at the City of Fairfield Wastewater Treatment Facility do our part in being environmentally friendly. Protection of the receiving waters is our #1 goal here at the facility.

The wastewater treatment industry is rapidly changing. Restrictions on effluent quality are increasing, Biosolids programs are changing, technology is moving forward, and the facility and collection system's infrastructure is growing in age.

The staff at the City of Fairfield Wastewater Treatment Facility takes great pride in staying one step ahead of the ever growing demands and changes in the wastewater treatment industry. Below is a list of some Capital Improvement Projects and their costs coming up in the near future.

 

2014

Sanitary Sewer Rehabilitation $200,000
Root Control Program $20,000
Manhole Rehabilitation Program $10,000
Channel Grinder Overhauls $24,000
Instrumentation Replacement Program $15,000
Generator Installation & MCC $180,000
Primary System Tank Overhaul $40,000
Video & Sewer Cleaning Equipment $6,000
Turblex Blower Service $23,000
Pavement Repairs & Replacement $25,000
Plant SCADA System Replacement $50,000
Facility Fencing $8,500
Biosolids Storage Building $250,000
Phosphorus Removal Evaluation $25,000
Dystor Dome Replacement $410,000
Sludge Thickener Building Renovation $15,000
Turblex Blower HMI Panel View $15,000
Digester 3 & 4 Valve Replacement $12,500
Aeration System Diffuser Replacement $45,000
Broadview List Station Roof Repair $16,000
Wastewater System Vulnerability Assessment $30,000
Remodel Lab $35,000

 

2015

Sanitary Sewer Rehabilitation $200,000
Root Control Program $20,000
Manhole Rehabilitation Program $10,000
Channel Grinder Replacement $50,000
Instrumentation Replacement $15,000
Generator Installation and MCC $180,000
Primary System Tank Overhaul $40,000
Video & Sewer Cleaning Equipment $35,000
Pavement Repairs and Replacement $15,000
Broadview Lift Station Valve Actuators $15,000
Phosphorus Removal Facilities $600,000
Wastewater Plant Concrete/Masonry $20,000
Monitoring Equipment  $12,000
Pump Overhaul/Replacement Program $30,000
Anaerobic Digester Cleaning $15,000
Digester Facade  $35,000
Raw Sewage Valve/Check Valve Replacement  $15,000
Wet Well Gate/Shaft Replacement $25,000
Primary Boiler Burner Assembly $55,000
Hycore Press Replacement $40,000

 

2016

Sanitary Sewer Rehabilitation $200,000
Root Control Program $20,000
Manhole Rehabilitation Program $10,000
Channel Grinder Replacement $50,000
Instrumentation Replacement  $15,000
Generator Installation and MCC $180,000
Primary System Tank Overhaul $40,000
Video & Sewer Cleaning Equipment $10,000
Wastewater Plant Concrete/Masonry $20,000
Monitoring Equipment  $12,000
Pump Overhaul/Replacement Program  $18,000
Anaerobic Digester Cleaning $15,000
Digester Facade $35,000
Digester External Mixer $125,000
Aeration Panel Replacement  $25,000
Digester Sedimentation $220,000
Administration Building Garage Expansion  $160,000
Blower Air Header Repair/Replacement $50,000
Wastewater
City of Fairfield
Fairfield, OH 45014
(513) 858-7775 - After Hours | E-mail

If you are experiencing a Sewer Emergency or have water backing up in your basement contact the Wastewater Treatment Facility at (513) 858-7775 - After Hours

> Manage Utilities